PLN RUPTL 2025–2034 | Investment & Grid Intelligence
Digitization of a user-provided 100-page partial RUPTL: decree and Chapters I–II. Twenty-one source-traced indicators, 109 candidate floating-solar reservoirs and smart-meter targets, with explicit evidence-quality boundaries.
1. National planning composition
Planned generation and storage, MW
National grid expansion
2. Floating solar: all 109 reservoir opportunities
Indicative potential by province
Cross-provincial Karangnongko shown as a separate label. Repeated Gembong is excluded only if the deduplication toggle is enabled.Filter reservoir register
Source Tabel 2.2, PDF pp.82–83. The terms Eksisting, Selesai, On Going, Baru describe the dam, not whether a floating PV plant is operational. A 20% reservoir-area potential is neither an energy yield nor an approved development.
| Source row | Reservoir | Province | Dam status | Area (ha) | Potential (MW) | PDF page |
|---|
3. Smart grid and AMI rollout targets
4. Grid connection due-diligence for AI data centers
5. Province annex extraction status
6. Investor assessment · energy security & AI infrastructure
01 · Demand confirmation is the gating factor
RUPTL uses customer confidence for large high-voltage loads: contracts, connection payments and grid construction are stronger evidence than MoUs. Apply this hierarchy to AI data-center announcements before treating them as firm PLN load.
Source: PDF pp.46, 53.02 · Site-level reliability is not a system-wide MW number
N-1 transmission and substation contingency planning is required, but this document does not prove N-1 availability for any AI campus. Request feeder, transformer, protection and energization studies.
Source: PDF pp.89–90.03 · Grid investment can precede peak-load bottlenecks
The RUPTL describes a typical 70–80% GI loading range for planning transformer reinforcement, subject to N-1 exceptions. This is a planning criterion, not evidence that Bekasi or Batang substations are currently near saturation.
Source: PDF p.90.04 · Reservoir solar is optionality, not bankable supply
Its 109 entries amount to around 13.9 GW of indicative area-based potential. The duplicate Gembong entry, trans-provincial Karangnongko and lack of procurement or grid-connection records prevent interpreting the sum as an executable PV investment portfolio.
Source: Table 2.2, PDF pp.82–83.05 · BESS investment needs duration and location
Nationally planned storage power of 10.256 GW does not specify hours of storage, deliverable energy in GWh, dispatch profile or which local data-center clusters benefit. BESS opportunities therefore require a separately verified regional siting and grid-services model.
Source: decree p.5; storage strategy pp.74–76.06 · Carbon claims require energy, not nameplate
The 2034 EBT target of 34.3% concerns electricity generation mix. The 42.569 GW EBT buildout is installed-capacity planning; neither proves renewable power actually contracted or delivered hourly to a data center.
Source: decree p.5.07 · Annexes are essential for location intelligence
The uploaded 100 pages name annex A4 (Kepulauan Riau), B3 (Jawa Barat) and B4 (Jawa Tengah), but do not contain their project-level schedules. No exact GI COD, additional MW or investor ranking should be inferred for these locations yet.
Source: PDF p.27.08 · Smart-meter data requires reconciliation
AMI implementation is an important operational technology signal, but the printed post-2033 roll-out series and the 2037 accompanying prose conflict. Any investor dashboard should show the contradiction rather than blending it into a verified adoption trend.
Source: PDF pp.98–99.Data files and provenance
Official planning indicators, AMI and investor policy dataset · sumber & metodologi SLI ↗ · Full 109-reservoir register · sumber & metodologi SLI ↗
Previously digitized national RUPTL dashboard · PLN actual baseline 2024 · AI electricity sensitivity 2026–2035
Provided PDF: 876718974-RUPTL-2025-2034-1.pdf, 100 pages, sha256 6b0a38077e64421c034b94f49bf97d05afc18ddfdedaf8e44607380c9a284ac1, approved 26 May 2025. Sources remain distinguishable: official target ≠ realized 2024 ≠ AI demand scenario.