RUPTL PLN 2025–2034 · Grid & Energy Investment

Interactive digitization of verifiable national RUPTL approval figures and selected regional transmission planning. Planned additions are not realized power-system capacities.

Generation and storage planned
69.512 MW
Transmission planned
47.758 kms
Substations planned
107.950 MVA
2034 renewable energy mix target
34,3%
Coverage: Core national planning figures come from the ESDM approval decree and PLN statements. The complete 1,253-page official RUPTL passed integrity checks and its 42 annex headings are indexed. A separate sampled PDF project-row register and selected operator status observations are available, but neither constitutes a complete province-level realized-investment census. Local grid-headroom, connection queues and PLN Statistics 2025 still require independent validation. This is not a complete digital twin of the RUPTL. View full official annex source index ↗.
Source-backed deep dive: Read digitalized RUPTL primary-source excerpt ↗ for 2022–2045 AMI targets, PLN N-1/substation criteria, BESS planning, and selected dam solar potential. Excerpt covers the first 100 PDF pages; detailed province project annexes remain outside it.

Planned supply additions · MW

Regional transmission · circuit-km (planned)

Indicative investment opportunity · trillion rupiah

Expanded source digitization: Open RUPTL uploaded excerpt deep-dive ↗ for page-referenced grid standards, AMI annual targets and 109 waterbody potential records. This 100-page excerpt does not include the provincial annex project schedules.

Crosswalk to AI data center investment clusters

ClusterRUPTL reporting regionGrid project specificityRelationship to national PLN network
Bekasi–KarawangJava–Madura–BaliSubstation project not yet extractedConnected to Java–Bali; system transmission totals cannot be assigned to local headroom.
BatangJava–Madura–BaliSubstation project not yet extractedLocal transformer and network completion evidence still needed.
Jakarta MetroJava–Madura–BaliSubstation project not yet extractedCloud region facilities undisclosed; metro grid mapping approximate.
BatamSumatra–Kalimantan aggregate in summarized sourceBatam / PLN Batam local project not isolatedNeed PLN Batam system and proposed Sumatra–Batam–Bintan interconnection project specifics.
Units matter: 69,512 MW includes generation AND storage. Energy mix share 34.3% is a targeted generation mix, not 34.3% of installed MW. MVA of substations is apparent-power equipment rating and cannot be interpreted as guaranteed MW headroom. Large national investment envelopes are proposed opportunities, not funds disbursed to data centers.

source-linked · sumber & metodologi SLI ↗ · Official ESDM approval